mpp
Assignment:
This exercise begins with a list of tasks for a wedding project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub tasks, create links between tasks and their predecessors, add resources, and make changes to the original plan.
A. Enter the following tasks, including the specified duration, specified predecessors, and specified resources. Tasks that are bolded are summary tasks and the indented tasks are sub tasks. Task List
B. Enter the following list of resources into the same Microsoft Project file that you entered the above task list. Resource List
C. Change the Project from being scheduled from a Start date, to being scheduled from a Finish Date. The Finish Date is the date of the wedding, November 12th, 2015.
D. Change the constraints on the following Tasks:
Task Constraint
Update list of Guests Attending Finish no later than November 10, 2015
Final Fitting Finish no later than November 6, 2015
Schedule Rehearsal Dinner Must start on November 11, 2015
Apply for Wedding License Finish no later than November 10, 2015
Finally, submit your finished homework assignment to Canvas.
Saving/Naming Your File:
When you save your file make sure that your name and the project number are included in it.