project schedule
Description
Develop Project Schedule
Project Schedule: Establish a project baseline at this time, define the tasks, start and finish dates, durations, predecessors (sequence of activities), resource names, and possibly cost. Project schedule should account for all of the activities that must happen. It must not be less than 30–50 activities and sub activities.
Tips: Start by looking at the WBS activities that you defined last week. Think about how you could decompose your work packages into activities and subactivities to complete this coffee house project. You should use all of the project artifacts (deliverables) you produced so far and the given project scenario to identify all of the activities that are needed.
You should be able to come up with 30–100 activities easily for your schedule baseline. Once those activities have been identified, finish your schedule by plugging in start and finish dates, durations, predecessor relationships, and adding cost and resource names. Resource names and cost can be added in the main summary page or directly in the resource sheet. Your project name must go in the first row, and all other activates should be indented under it. You should link all activities to summary tasks and subactivities to the main activity. You may make assumptions for any of this work, and estimates do not need to be real. You should save the finished project file as: “Week 3 deliverable_your name.”